Recommended that the Executive requested Full Council approve the following additions to the Capital Programme, which would be funded through borrowing:
1) Add the following to the Capital Programme for 2019/20
a. The sum of £100,000 be allocated to the wall design works at Splash Point; and
b. The sum of £100,000 be allocated to the wall design works at East Quay.
2) Add the following to the Capital Programme for 2020/21
a. The sum of £500,000 be allocated to reinforce the East Quay wall in the central section; and
b. The sum of £40,000 for project management resource to deliver this project to its conclusion.