East Quay Wall

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Recommended that the Executive requested Full Council approve the following additions to the Capital Programme, which would be funded through borrowing:

1)    Add the following to the Capital Programme for 2019/20

a.    The sum of £100,000 be allocated to the wall design works at Splash Point; and

b.    The sum of £100,000 be allocated to the wall design works at East Quay.

2)    Add the following to the Capital Programme for 2020/21

a.    The sum of £500,000 be allocated to reinforce the East Quay wall in the central section; and

b.    The sum of £40,000 for project management resource to deliver this project to its conclusion.

Report author: Chris Hall

Publication date: 23/01/2020

Date of decision: 22/01/2020

Decided at meeting: 22/01/2020 - SWT Executive

Accompanying Documents: